Budget vs. actual, the right way

By Raz DanoukhApr 5, 2026 4 minute read

Paired budget and actual cost bars diverging on a dark chart with an alert marker on the overrun

Most budget-vs-actual reports compare the wrong two numbers. Budget minus spent tells you what's gone — not what's coming.

The column everyone forgets

Committed costs. Signed purchase orders and subcontracts are money you've already promised, even if no invoice has arrived. A report without committed costs always looks healthier than the job really is.

The honest report

  • Budget — what you planned
  • Committed — what you've promised
  • Actual — what you've been billed
  • Projected at completion — committed plus actuals plus estimate to finish

Keep it live

When change orders update the budget the day they're approved, variance stops being a surprise at month end.